2015 South Wastewater Treatment Facility – Fox Metro Water Reclamation District

Project consisted of the construction of a headworks building, a primary sludge pump
station, primary clarifiers, BNR tanks, a secondary control building, final clarifiers, and
ferric chloride storage. Also included was all architectural, civil, process, mechanical,
electrical, instrumentation and control works for a complete and functional wastewater treatment facility.

View More in Waste Water/Water Treatment

City Water Light Power – Water Works Improvements Projects, Contract 2 – Clearwell No. 3

Construction of a cast-in-place reinforced concrete clearwell, associated excavation, final grading, seeding and fertilizing, erosion control, surface and subsurface drainage, buried storm sewer and drainage piping, boring and jacking of pipe casing, protection of and shoring for adjacent utilities, manhole…

Waterloo Wastewater Treatment Facility

This project included raw sewage intake structure; mechanical bar screen; grit removal units; flow metering, submersible pumps with VFD’s; aerated digester tanks; SBR process pump rooms and blowers; MCC rooms; digester blowers; digester sludge pumps; and various other items and…