Rock River Secondary Treatment Improvements

Works consisted of construction, modifications and additions to the secondary treatment facilities.  This included the construction of a new treatment process train and separation of the existing secondary treatment process into three processes.

Rocky Fork Wastewater Treatment Facility

The project consisted of the construction of a new wastewater treatment facility. The treatment process used Siemens Orbal® treatment equipment with two (2) Siemens Tow-Bro® secondary clarifiers that have been pre-procured by the District. Other major treatment equipment included influent pumps,…

South Beloit Wastewater Treatment Plant Improvements

The South Beloit WWTP project is a multi-phase project. It entails the demolition of numerous structures along with modifications to existing structures to create the new plant. Construction will include a new headworks building, control building, clarifiers, sludge dewatering building,…

Spring Creek Wastewater Treatment Plant Phase 1 and Phase 2

Phase 1 Construction included site work, diversion structure, influent sewer, administration and operations building, disinfection building, out fall sewer and cascade aerator. Phase 2 Construction included site work, headworks building and equipment, activated sludge structure and equipment and site utilities….

St. Charles Main Wastewater Treatment Facility – 2002 Nitrification Improvements

Modified headworks diversion structure; rehabilitated ferric chloride and grit buildings; replaced scum troughs on primary clarifiers; constructed 2.8 million gallons of additional aeration basins; constructed a new blower building; rehabilitated existing aeration basins; installed baffles in existing final clarifiers; replaced…