Bloomington, IL
The project consists of the construction and improvement of water distribution facilities throughout the existing distribution system. The scope of work includes sitework, yard piping, structural and architectural improvements, process piping and equipment, plumbing, heating, ventilation, air conditioning (HVAC), electrical systems, and instrumentation and controls. Major project components include the construction of a new 22.5 million gallons per day (MGD) water pump station, upgrades to an existing 4.5 MGD booster station, construction of two new 5-million-gallon (MG) ground storage tanks, installation of a new 36-inch water main, improvements to existing water mains, and rehabilitation of an existing 0.4 MG elevated water storage tank.